Build a manufacturing cost estimate
Connect material, setup, runtime, outside processing and inspection into an explicit per-part estimate.
Research draft — not customer-confirmed
On this page
Build the estimate around the production route
A useful estimate explains what work is included, how often it occurs, and how many accepted parts share its cost. Start with the part's route rather than adding unrelated hourly rates.
Separate batch costs, such as setup, from recurring part costs. Then add outside services and other charges on their actual billing basis. This structure follows the components described by Boothroyd Dewhurst's machining cost guide.
Connect each cost to its driver
| Cost | Typical driver to establish | Detailed guide |
|---|---|---|
| Material | Purchased stock and attributable consumption | Stock forms and scrap recovery |
| Setup | Required setup events and resources occupied | Setup amortization |
| Processing | Applicable duration and included rate components | Machine-hour rates |
| Tool consumption | Usable life, changes and good output | Tool-life allocation |
| Outside processing | Supplier price, minimum charge and lot definition | Minimum lot charges |
Inspection and handling may be separate activities or included in another rate. Name the convention once so the same work is not charged twice. The job-order costing guide explains accumulation and reconciliation after production.
Worked example: a 100-part bracket order
This invented USD example assumes 100 accepted brackets, no rejects, one setup, and a sequential route. Material is $5 per bracket. Setup uses the $300 resource burden in the setup guide. Runtime is four minutes per bracket at an explicitly inclusive $60/hour. Outside finishing costs $2 per part subject to a $250 lot minimum. Inspection is a separate $50 batch activity, excluded from the other amounts.
| Component | Calculation | Batch cost |
|---|---|---|
| Material | 100 × $5 | $500 |
| Setup | One event | $300 |
| Runtime | 100 × 4/60 hours × $60/hour | $400 |
| Outside finishing | Greater of $200 and $250 | $250 |
| Inspection | One batch activity | $50 |
| Total | Sum of distinct components | $1,500 |
The estimate is $15 per accepted part. The minimum-charge calculation applies only because the fictional supplier's terms explicitly define it that way. Taxes, freight, selling expenses and profit are excluded.
What changes when the order changes?
At 20 accepted parts, with the same assumptions and one setup, the total becomes $100 + $300 + $80 + $250 + $50 = $780, or $39 per part. Setup and the supplier's minimum matter much more at the smaller quantity.
This is a sensitivity example, not a prediction that every smaller order follows those rates. A different route, inspection scope, tooling need or supplier quote changes the inputs. Repeated deliveries may require repeated setups and outside-processing lots.
For laser-cut components, laser timing explains how cutting, piercing and other activities contribute to duration. For welded components, porosity troubleshooting shows why the original route may need additional examination or repair. Neither a cycle-time model nor a defect observation determines those additional costs automatically.
Keep cost, price and delivery separate
A modeled production cost is not a selling price. Machine-hour rates distinguishes cost rates, markup and margin. Contribution margin addresses a different cost basis again.
Nor does adding operation durations produce a promised delivery date. Queues, outside-service timing and calendars require scheduling information. Compare actual completion and consumption with the estimate using the same quantity and activity boundaries before changing future assumptions.